armasuisse Immobilien commissioned us as general contractor for the handling and construction of 2 halls for the new bridge laying vehicles. The contracts for both halls were awarded including environmental works, parking spaces, façade and roof covering, alarm system and BMA.
One contact for all internal and external interfaces
The client entrusted us with the additional mandate of coordinating the execution of this building project. As a result, we supported the client as a contact partner for all internal and external interfaces.
The preceding deconstruction, the new connection of water, electricity, and telephone connection as well as the securing of public and company traffic were also part of our services. A total of 130 tonnes of steel were used in the 45 x 15 x 8 metres and 34 x 15 x 8 metres car park.
Below budget
By integrating elements of Last Planner and Lean Construction, we were able to hand over the building to the client one month ahead of schedule. We were able to come in under budget.
Execution
2014/2016Construction costs
CHF 4.5 million
Cooperation
The project was carried out in collaboration with internal DDPS offices and external planners directly commissioned for the surroundings and traffic development.
Client
armasuisse Real Estate, Construction Management East
Services
- Deconstruction
- SIA phase 31 to 33
- SIA phase 41
- SIA phase 51 to 53
- Support of the client as realisation coordinator
- The performance of the hall incl. hall access was awarded in the TU mandate.